2015 HPC Upgrade

During Summer 2015, the HPC will replace and upgrade equipment as part of our normal 3-year cycle.  The tentative timeline for the upgrade efforts are: July 1, 2015 through July 31, 2015.

Upon completion of the upgrade, the HPC configuration will consist of:

Master Nodes and Login Nodes
Scyld HPC Cloud Appliance Suite
         2 Relion 1800s Cloud Controller
        2 IceBreaker 2812 Intel Server - VM Host & CEPH

Compute Nodes
12 Relion 2940 4x Compute nodes 64GB (Thin)
1 Relion 2940 4x Compute node 128 (Fat)
2 Relion 1900 Server - Compute Node 512GB (Super Fat)
1 Relion 2804e Server - 4P Compute Node 1TB (Hi-Mem)
8 Relion 1903GT Server - GPU Compute Node 128GB (2 x Tesla K40m)
6 Relion 900 Server - Compute Node 16TB Scratch
6 Relion 900 Server - Compute Node 8TB Scratch

Storage
Panasas 367 TB Storage solution