The following list is current and ongoing UofM projects.
Administration Breezeway
Scope:Install receptacles for use by students, add reading lighting, and repair existing
seating. Project Manager is Nat Youngblood (ext. 5320)
Impact Area:Administration: Staff and Students Common Space
Project Timelines:Complete by Jan. 12
Start and Stop Dates: 10/13/25 – 1/12/26
Building Name:Administration Building
Room Numbers:199N, 138, 199P
Update: In progress-target completion date changed to Feb. 20 due to material delays.
Administration OIE Security
Scope: Open interior wall to create a single point of entry. Rear exit will remain emergency
egress only. Project Manager is Racheal Walker
Impact Area:Admin
Project Timelines:Completion target August 30, 2026
Start and Stop Dates:5/1/2026 - 8/30/2026
Building Name: Administration Building
Room Numbers: All Classrooms
Update: Reviewing with Police Services
Carney-Johnston Kitchenette
Scope:Enhance the existing kitchenette by installing an island cooktop with fire suppression,
circulating ventilation, kitchen sink and associated amenities. Project Manager is
Gerry Keen (ext. 2218).
Impact Area:Residence Life
Project Timelines:Complete by February 26 ,2026
Start and Stop Dates:December 16, 2025 – February 26, 2026, pending fire marshall approvals during the
holiday season.
Building Name: Carney Johnston
Room Numbers: Lobby/Commons
Update:All work is complete except fire suppression system. Installation and inspections
are being scheduled.
Chemistry Building Roof Replacement
Scope: Overall project completion target date is April 30, 2026. Project Manager is Phyllis
Holder
Impact Area:Academic/Research
Project Timelines:Completion target April 30, 2026
Start and Stop Dates:12/12/25 – 4/30/2026
Building Name: M.Smith Building
Room Numbers: Roof work only
Update:Demolition and Construction is target for completion by April 30,2026.
Campus Access Control
Scope: Campus Wide Perimeter Door Access Control.
Impact Area:Academic
Project Timelines:TBD
Start and Stop Dates:TBD
Building Name: Multiple Buildings
Room Numbers: Main Campus Buildings
Update:Upgrade all Main Campus Buildings with Perimeter Door Access Controls
Campus Classroom Door Security
Scope: Overall project completion target date is August 30, 2026. Project Manager is Racheal
Walker
Impact Area:Academic
Project Timelines:Completion target August 30, 2026
Start and Stop Dates:12/12/25 – 8/30/2026
Building Name: Multiple Buildings
Room Numbers: All Classrooms
Update:Upgrade all classroom doors with ADA approved bolt/thumb/indicator locks. All doors
being reviewed and documented.
Clement Hall Fan coil controls
Scope:Provide selected fan coil controls improvements throughout the building. Project manager
is Nat Youngblood.
Impact Area:Academic
Project Timelines:Summer ,2026
Start and Stop Dates:May 1, 2025 – August 30, 2026, pending fire marshall approvals during the holiday
season.
Building Name: Clement Hall
Room Numbers: Entire building
Update: Finalizing details of work by 3/1/26
Engineering Solar Smart grid lab
Scope:Install solar farm with fencing including electrical distribution and lab setup. Project
Manager is Racheal Walker (ext. 2076)
Impact Area:Research
Project Timelines:Complete by 5/30/26
Start and Stop Dates:9/1/25 – 5/30/26
Building Name: Building 52
Room Numbers: Paint room
Update:Installation Inspected by State Electrical Code Enforcement. Code required changes
being evaluated.
ERIC Laser Cutter Exhaust
Scope: Install a new exhaust system for the large laser cutter in the electronics fabrication
lab. Project Manager is Jimma Owens (ext. 2076).
Impact Area:Academics Lab/Research
Project Timelines:Complete by 3/30/26
Start and Stop Dates:12/16/25 – 3/30/26
Building Name: Edwards Research and Innovation Center
Room Numbers: 111, 102
Update:In progress-competion target is March 30, 2026 due to funding delays and equipment
delays.
Fieldhouse Gymnasium Center Furnaces
Scope: Install 2-400,000BTU Furnaces in each of the two gymnasiums along the East of the
building. Project Manager is Swazoo Claybon (ext. 2076).
Update:In Progress-target completion 2/26/26 due to delayed equipment delivery.
Fieldhouse Domestic Hot Water Plant
Scope:Install a heat exchanger-based system to run with the main building heating plant.
This will include heat exchanger and pump integration. Project Manager is Swazoo Claybon
(ext. 2076).
Impact Area:Athletics/Academics/Research
Project Timelines:Complete final inspection by 2/26/26
Start and Stop Dates:11/13/25 – 2/26/26
Building Name: Elma Neal Roane Fieldhouse
Room Numbers: 147
Update: Substantially Complete; system is in operation
Fieldhouse Heating Hot Water Boiler
Scope: Add a redundant 850,000BTU Condensing boiler for the building. Project Manager is
Swazoo Claybon (ext. 2076).
Impact Area:Athletics/Academics/Research
Project Timelines:Complete final inspection by 2/26/26
Start and Stop Dates:11/13/25 – 2/26/26
Building Name: Elma Neal Roane Fieldhouse
Room Numbers: 259A1, 259A1A
Update: Project target completion is adjusted to 2/26/26
Fieldhouse Controls Improvements
Scope: Provide controls improvements on boiler controls and outside air damper controls
Impact Area:Athletics/Academics/Research
Project Timelines:Summer 2026
Start and Stop Dates:5/1/26 – 8/30/26
Building Name: Elma Neal Roane Fieldhouse
Room Numbers: Entire Building
Update: Planning in progress
Fogelman B&E Renovation (SBC) Moving Logistics
Scope: Move all lab computers and furniture necessary to reconfigure for Spring academic
classes to begin on 1/19/26. Logistics will include necessary electrical, network
improvements, computer moving. All computer labs and Wilson school operations must
be ready for the Spring semester final setup by 1/12/26. Overall project completion
is targeted for December 2026. Project Manager is Phyllis Holder (ext 3940).
Impact Area:Academic
Project Timelines:Complete all academic logistics by 1/12/26
Start and Stop Dates:12/12/25 – 3/1/26
Building Name: Fogelman College of Business and Economics Classroom Bldg.
Room Numbers: Building closing for construction
Update: In Progress-logistics schedule is on track through March 1 delivery to Construction
Phase
Fogelman Administration Building Moving Logistics
Scope: Assist moving all faculty and staff out of the building by 12/17 - 12/19/26. Begin
moving all furniture and 2 boxes per person to storage on 1/19/26. Final date will
depend on final disposition of furniture. Overall project completion is targeted for
December 2026. Project Manager is Phyllis Holder (ext 3940).
Impact Area:Academic
Project Timelines:Completion by February, 2026
Start and Stop Dates:12/17/25 – 3/1/2026
Building Name: Fogelman Administration building
Room Numbers: Entire building
Update: In Progress-logistics schedule is on track through March 1 delivery to Construction
Phase
Johnson Hall AHU3 – Phase 2
Scope: Relocate existing AHU3 unit to new mechanical room until the new unit arrives. Project
Manager is Phyllis Holder (ext. 3940).
Update: Equipment has shipped. Completion target by April 30 pending delivery of the HVAC
equipment.
Jones TigerDen Upgrades
Scope: Reconfigure the Tiger Den to enhance operations and aesthetics. Project Manager is
Racheal Walker.
Impact Area:Dining Services
Project Timelines:Summer 2026
Start and Stop Dates:5/8/26 – 8/30/26
Building Name: Jones Cafeteria Building
Room Numbers: Entire section of building
Update: Planning is in progress.
Lambuth Hyde Hall DPT Program Improvements Ph2
Scope: Reviewing scope items now. Gerry Keen is Project Manager
Impact Area:Doctor of Physical Therapy Program
Project Timelines: Target Summer 2026
Start and Stop Dates:Target Summer 2026
Building Name: Hyde Hall
Room Numbers: Entire building.
Update: All Phase 1 work is completed
Life Science Roof Replacement
Scope: Overall project completion target date is April 30, 2026. Project Manager is Phyllis
Holder
Impact Area:Academic/Research
Project Timelines:Completion target April 30, 2026
Start and Stop Dates:12/12/25 – 4/30/2026
Building Name: Life Sciences Building
Room Numbers: Roof work only
Update:Demolition and Construction is target for completion by April 30,2026.
Life Sciences Basement HVAC Replacement
Scope: Demo old Steam Piping including asbestos abatement. Relocate research animal labs.
Demo old HVAC system and replace with new VAV system and new controls. Overall project
completion target date is April 30, 2026. Project Manager is Phyllis Holder.
Impact Area:Research
Project Timelines:Complete by 1/12/26
Start and Stop Dates:12/12/25 – 2/26/26
Building Name: Life Sciences building
Room Numbers: Entire Basement
Update: Construction is substantially complete and operational. Environmental Test and Balance
and final commissioning in progress.
Life Sciences Building Automation Controls Improvements
Scope: Upgrade selected controls systems including Dampers and VAV systems. Project Manager
is Jimma Owens
Impact Area:Building
Project Timelines:Complete by 9/30/26
Start and Stop Dates:5/1/26 thru 9/30/26
Building Name: Life Sciences building
Room Numbers: Entire Building
Update: Construction is substantially complete and operational. Environmental Test and Balance
and final commissioning in progress.
Mitchell Hall Fan Coil Controls
Scope: Upgrade selected fan coil systems with modified local control system. Project manager
is Nat Youngblood.
Impact Area:Academic
Project Timelines:Complete by 8/30/26
Start and Stop Dates:5/1/26 – 8/30/26
Building Name: Mitchell Hall
Room Numbers: Entire building
Update: Planning in progress.
Patterson Hall Fan Coil Controls Upgrade – Phase 3
Scope: Interior spaces of the building will be the focus to improve functionality. Planning
is in progress. Project Manager is Nat Youngblood.
Impact Area:Academics
Project Timelines:Complete by 8/30/26
Start and Stop Dates:5/1/26 – 8/30/26
Building Name: Patterson Hall
Room Numbers: Entire Building
Update:Planning in progress
South Hall Domestic Boiler - ResLife
Scope: Install new domestic boiler plant with redundancy. Upgrade the boiler room to meet
2021 IFC. Install backflow device. Obtain all State and Local code inspections. Project
Manager is Swazoo Claybon (2076).
Impact Area:Residence Life
Project Timelines:Complete by 2/26/26
Start and Stop Dates:11/3/25 – 2/26/26
Building Name: South Hall
Room Numbers: B007A
Update: Boiler installation is complete and running. Final inspection items in progress.
Utility – Park Ave. Campus Water Wells (MLGW) Ph2 Main
Scope:Install Collecting Water main piping to the North Water Well. Project Manager is Swazoo
Claybon (ext. 2076).
Impact Area:Residence Life
Project Timelines:Complete by 5/30/26 (Pending Weather)
Start and Stop Dates:10/13/25 – 5/30/26
Building Name:Graduate Student Family Housing / North Buford Ellington Rd.
Room Numbers: Road work/ Piping Main.
Update:Reviewing damage to university systems with MLGW. Establishing date to remobilize
the project.