The following list is current and ongoing UofM projects.
Administration Building Breezeway
Scope: Install receptacles for use by students, add reading lighting, and repair existing
seating. Project Manager is Nat Youngblood (ext. 5320)
Impact Area: Administration: Staff and Students Common Space
Project Timelines: Complete by January 12, 2026
Start and Stop Dates: 10/13/25 – 1/12/26
Building Name: Administration Building
Room Numbers: 199N, 138, 199P
Campus Driveway Repairs (2025)
Scope: Replace concrete and gate sensor at several access gates including Lot 55, Lot 30,
Veterans St. entry to Lots 25/26/27, and Holiday Inn entry to Lot 42. Project Manager
is Nat Youngblood (ext. 5320)
Scope: Enhance the existing kitchenette by installing an island cooktop with fire suppression,
circulating ventilation, kitchen sink and associated amenities. Project Manager is
Gerry Keen (ext. 2218).
Impact Area: Residence Life
Project Timelines: Complete by January 19,2026
Start and Stop Dates: December 16, 2025 – January 19, 2026, pending fire marshall approvals during the
holiday season.
Building Name: Carney Johnston
Room Numbers: Lobby/Commons
Central Boiler Plant Demolition – Flue Stack
Scope: Demolish and remove the flue stack from Boiler #5/ seal the roof deck/maintain roof
warranty. Project Manager is Jake Wilson (ext. 2485).
Impact Area: Physical Plant Operations
Project Timelines: Complete by January 19, 2026
Start and Stop Dates: 12/12/25 – 1/19/26
Building Name: Central Boiler Plant Bldg 151
Room Numbers: 100
Central Boiler Plant Softener and Blowdown
Scope: Install new water softener/chemical treatment system. Install a partial automatic
blowdown system. Finalize code inspection. Project Manager is Swazoo Claybon (ext.
2076).
Impact Area: Physical Plant Operations
Project Timelines: Complete by January 19, 2026
Start and Stop Dates: 8/4/25 – 1/19/26
Building Name: Main Boiler Plant
Room Numbers: 100
CERI EQ4 Data Center Humidity Control HVAC
Scope: Replace the HVAC Leibert unit with new 10Ton Computer Room HVAC. Project Manager is
Swazoo Claybon (ext. 2076).
Impact Area: Research
Project Timelines: Complete by 1/12/26
Start and Stop Dates: 10/13/25 – 1/12/26
Building Name: CERI EQ4
Room Numbers: 218
Chemistry (JMSmith) 405 Structural Repairs
Scope: Repair major structural spalling concrete with SIKA system and protect structural
rebar. Project Manager is Swazoo Claybon (ext. 2076).
Impact Area: Research
Project Timelines: Complete by 1/16/26
Start and Stop Dates: 10/13/25 – 1/16/26
Building Name: J.M.Smith Hall
Room Numbers: Rm 405
Chemistry (JMSmith) 407 Structural Repairs
Scope: Repair major structural spalling concrete with SIKA system and protect structural
rebar. Project Manager is Swazoo Claybon (ext. 2076).
Scope: Install LED surface mount lighting in teaching labs on 1st and 3rd floors including 1 research lab. Project Manager is Racheal Walker (Racheal.Walker@memphis.edu).
Chemistry Teaching Labs improvements – paint and patch
Scope: Repair lab cabinets including sanding and staining as needed. Miscellaneous painting/wall
and floor repairs as needed. Project Manager is Racheal Walker (Racheal.Walker@memphis.edu).
Impact Area: Academic Labs
Project Timelines: Complete by 1/12/26
Start and Stop Dates: 6/2/25 – 1/12/26
Building Name: J.M. Smith Chemistry
Room Numbers: 103, 111, 113, 121, 123, 131, 317
Chemistry fume Hood commissioning
Scope: Provide Testing and functional analysis of all fume hoods in the Chemistry facility.
Project Manager is Lynn Hicks (jlhicks2@memphis.edu).
Impact Area: Academic Labs/ Research
Project Timelines: Complete the Analysis by 1/12/26
Start and Stop Dates: 6/2/25 – 1/12/26
Building Name: J.M. Smith Chemistry
Room Numbers: All fume hood systems throughout the entire facility including roof exhaust fans (analysis
available for more details).
Chemistry Roof Replacement – Demolition only
Scope: Complete allnoisyconcrete demolition for roofing project by 1/12/26. Overall project completion target
date is April 30, 2026. Project Manager is Lynn Hicks (jlhicks2@memphis.edu).
Impact Area: Academics/Research
Project Timelines: Complete by 1/12/26
Start and Stop Dates: 12/12/25 – 1/12/26
Building Name: J.M.Smith Chemistry
Room Numbers: Concrete Demolition on roof only
Engineering Technology First Floor Ladies’ Room
Scope: Demo the old hand wash area and install new ladies’ room including all new fixtures,
tile, lighting, finishes. Project Manager is Phyllis Holder (ext 3940).
Impact Area: Academic/Research General
Project Timelines: Complete by 1/12/26
Start and Stop Dates: 6/2/25 – 1/12/26
Building Name: Engineering Technology
Room Numbers: 113
Engineering Solar Smart grid lab
Scope: Install solar farm with fencing including electrical distribution and lab setup.
Project Manager is Swazoo Claybon (ext. 2076)
Impact Area: Research
Project Timelines: Complete by 1/19/26
Start and Stop Dates: 9/1/25 – 1/19/26
Building Name: Building 52
Room Numbers: Paint room
ERIC/Stem Laser Cutter Exhaust
Scope: Install a new exhaust system for the large laser cutter in the electronics fabrication
lab. Project Manager is Swazoo Claybon (ext. 2076).
Impact Area: Academics Lab/Research
Project Timelines: Complete by 1/19/26
Start and Stop Dates: 12/16/25 – 1/19/26
Building Name: ERIC/Engineering/Stem
Room Numbers: 111, 102
Fieldhouse Gymnasium Center Furnaces
Scope: Install 2-400,000BTU Furnaces in each of the two gymnasiums along the East of the
building. Project Manager is Swazoo Claybon (ext. 2076).
Impact Area: Health Science Research/University Schools
Project Timelines: Complete by 1/19/26
Start and Stop Dates: 12/16/25 – 1/19/26
Building Name: Elma Neal Roane Fieldhouse
Room Numbers: 254, 258
Fieldhouse Domestic Hot Water Plant
Scope: Install a heat exchanger-based system to run with the main building heating plant.
This will include heat exchanger and pump integration. Project Manager is Swazoo Claybon
(ext. 2076).
Impact Area: Athletics/Academics/Research
Project Timelines: Complete final inspection by 1/19/26
Start and Stop Dates: 11/13/25 – 1/19/26
Building Name: Elma Neal Roane Fieldhouse
Room Numbers:147
Fieldhouse Heating Hot Water Boiler
Scope: Add a redundant 850,000BTU Condensing boiler for the building. Project Manager is
Swazoo Claybon (ext. 2076).
Impact Area: Athletics/Academics/Research
Project Timelines: Complete final inspection by 1/19/26
Start and Stop Dates: 11/13/25 – 1/19/26
Building Name: Elma Neal Roane Fieldhouse
Room Numbers: 259A1, 259A1A
Fogelman B&E Renovation (SBC) Moving Logistics
Scope: Move all lab computers and furniture necessary to reconfigure for Spring academic
classes to begin on 1/19/26. Logistics will include necessary electrical, network
improvements, computer moving. All computer labs and Wilson school operations must
be ready for the Spring semester final setup by 1/12/26. Overall project completion
is targeted for December 2026. Project Manager is Phyllis Holder (ext 3940).
Impact Area: Academic
Project Timelines: Complete all academic logistics by 1/12/26
Start and Stop Dates: 12/12/25 – 1/12/26
Building Name: Fogelman College of Business and Economics Classroom Bldg.
Room Numbers: Building closing for construction
Fogelman Administration Building Moving Logistics
Scope: Assist moving all faculty and staff out of the building by 12/17 - 12/19/26. Begin
moving all furniture and 2 boxes per person to storage on 1/19/26. Final date will
depend on final disposition of furniture. Overall project completion is targeted for
December 2026. Project Manager is Phyllis Holder (ext 3940).
Impact Area: Academic
Project Timelines: Completion by February, 2026
Start and Stop Dates: 12/17/25 – February, 2026
Building Name: Fogelman Administration building
Room Numbers: Entire building
Johnson Hall AHU3 – Phase 1
Scope: Relocate existing AHU3 unit to new mechanical room until the new unit arrives. Project
Manager is Phyllis Holder (ext. 3940).
Scope: Remodeling of assigned DPT Program classroom/lab/office areas including cleaning/asbestos
abatement, painting, electrical, flooring, wall demo/reconfigure, door repairs with
hardware upgrade, ceiling repairs, furniture/equipment A/V, and lighting. Refurbishment
of public corridors, toilet rooms, and stairwells. Project Manager is Gerry Keen (ext.
2218).
Impact Area: Doctor of Physical Therapy Program
Project Timelines: Complete Phase 1 building construction by 12/19/25. Third floor Furniture is not
part of Phase 1 construction.
Start and Stop Dates: 1/6/25 – 1/12/26
Building Name: Hyde Hall
Room Numbers: Entire ground floor, public corridors and toilet rooms throughout building, stairwells,
114/116,115,115A,115B,117A,117B,118,213,217, entire 3rd floor.
Lambuth Hyde Hall Fire Alarm Upgrade / Basement HVAC
Scope: Upgrade the entire fire alarm system to meet all NFPA 72 requirements. Integrate
fire alarm system with the elevator controls. Demolish all old fire alarm systems.
Replace HVAC system serving the ground floor to meet the design air volume requirements
including dehumidification control. Replace/Clean reheat coils as needed. Install
new control valves, manual ball valves, and thermostats. Install new building automation
system and network for online monitoring. Provide ground floor duct cleaning. Project
Manager is Swazoo Claybon (ext. 2076).
Impact Area: Doctor of Physical Therapy Program
Project Timelines: Complete Phase 1 construction by 12/19/25.
Start and Stop Dates: 1/6/25 – 12/19/25
Building Name: Hyde Hall
Room Numbers: Entire Building
Life Science Roof Replacement/Demolition
Scope: Target noisy demolition work during the winter break with academic programs offline.
Overall project completion target date is April 30, 2026. Project Manager is Lynn
Hicks (jlhicks2@memphis.edu).
Impact Area: Academic/Research
Project Timelines: Complete all noisy demolition by 1/12/26
Start and Stop Dates: 12/12/25 – 1/12/26
Building Name: Life Sciences Building
Room Numbers: Roof work only
Life Sciences Basement HVAC Replacement
Scope: Demo old Steam Piping including asbestos abatement. Relocate research animal labs.
Demo old HVAC system and replace with new VAV system and new controls. Overall project
completion target date is April 30, 2026. Project Manager is Lynn Hicks (jlhicks2@memphis.edu).
Impact Area: Research
Project Timelines: Complete by 1/12/26
Start and Stop Dates: 12/12/25 – 1/12/26
Building Name: Life Sciences building
Room Numbers: Entire Basement
McWherter Library Elevator HVAC/disruptive construction
Scope: Install all elevator cooling systems including above ceiling and noisy work. Cap off
large HVAC duct above ceiling. Overall elevator project complete date is 10/1/26.
Project Manager is Lynn Hicks (jlhicks2@memphis.edu).
Impact Area: University library/elevator areas
Project Timelines: Complete by 1/12/25
Start and Stop Dates: 12/12/25 – 1/12/25
Building Name: McWherter Library
Room Numbers: Elevator common space
McWherter Library Special Collections/Leibert/Humidity Control
Scope: Replace 2–10-ton computer room hvac units. Crane required for 1 day. Project Manager
is Swazoo Claybon (ext. 2076).
Impact Area: University Library/ Special Collections
Project Timelines: Complete by 1/12/26
Start and Stop Dates: 12/12/25 – 1/12/26
Building Name: McWherter Library
Room Numbers: 411, 432
McWherter Library – Einstein Bagels Remodel
Scope: Upgrade point of sale technology. Provide painting and interiors enhancements. Project
Manager is Swazoo Claybon (ext. 2076).
Impact Area: Dining Services
Project Timelines: Complete by 1/19/26
Start and Stop Dates: 11/24/25 – 1/19/26
Building Name: McWherter Library
Room Number: Einstein Bagel Shop
Mitchell Hall Roofing Overlay
Scope: Limited roofing upgrade. This project will overlay a single ply membrane roof on top
of the existing roof and encapsulate the parapet walls. This will eliminate the new
leaks for approximately 25% of a full replacement and include a 2-year warranty. Project
Manager is Nat Youngblood (ext. 5320).
Impact Area: Academic
Project Timelines: Complete by 1/19/26 (pending funding)
Start and Stop Dates: 12/12/25 – 1/19/26
Building Name: Mitchell Hall
Room Numbers: Roofing only
Mitchell Hall HVAC Select Fresh Air Corrections
Scope: Duct fresh air and circulating air in all offices in suite 301. Duct fresh air into
large meeting room 223 and into the chair’s suite 219/221. Project Manager is Nat
Youngblood (ext. 5320).
Patterson Hall Fan Coil Controls Upgrade – Phase 2
Scope: Upgrade all fan coil units in the building to include new higher quality control valves,
new ball valves, and tightened threaded flex connectors. Include controls startup
and testing. 4 risers only offline at a time to maintain building heat. Hot water
will be offline when the transformers are down. Project Manager is Swazoo Claybon
(ext. 2076).
Impact Area: Academics
Project Timelines: Complete by 1/12/26
Start and Stop Dates: 12/15/25 – 1/12/26
Building Name: Patterson Hall
Room Numbers: Entire Building
Patterson Hall Storm Damage/ Insurance - Flooring
Scope: Repair LVT floor in room 125 entry area. Project Manager is Swazoo Claybon (ext. 2076).
Impact Area: Academic
Project Timelines: Complete by 1/12/26
Start and Stop Dates: 12/12/25 – 1/12/26
Building Name: Patterson Hall
Room Numbers: 125
Rawls Hall Stair Rails
Scope: Install egress rails (5 handrails) on East steps per 2021 IFC code. Project Manager
is Nat Youngblood (ext. 5320).
Impact Area: Residence Life
Project Timelines: Complete by 1/19/26
Start and Stop Dates: 12/12/25 – 1/19/26
Building Name: Rawls Hall
Room Numbers: Exterior entry only
SFPAC Spotlight Room HVAC
Scope: Install fan system to inject cooling and displace the heat from the spotlights in
the spotlight booth. This is required so that the operators can keep the doors closed
and provide quiet operation. Project Manager is Nat Youngblood (ext. 5320).
Impact Area: Academics/Public performances
Project Timelines: Complete by 1/12/26
Start and Stop Dates: 10/13/25 – 1/12/26
Building Name: Scheidt Family Performing Arts Center
Room Numbers: 3000
South Hall Domestic Boiler - ResLife
Scope: Install new domestic boiler plant with redundancy. Upgrade the boiler room to meet
2021 IFC. Install backflow device. Obtain all State and Local code inspections. Project
Manager is Swazoo Claybon (2076).
Impact Area: Residence Life
Project Timelines: Complete by 12/19/25
Start and Stop Dates: 11/3/25 – 12/19/25 (Pending equipment delivery)
Building Name: South Hall
Room Numbers: B007A
Utility – South Campus Water Wells (MLGW) Ph2 Main
Scope: Complete Collecting Water main piping to the North Water Well. Project Manager is
Swazoo Claybon (ext. 2076).
Impact Area: Residence Life
Project Timelines: Complete by 1/19/26 (Pending Weather)
Start and Stop Dates: 10/13/25 – 1/19/26
Building Name: Graduate Student Family Housing / North Buford Ellington Rd.
Room Numbers: Road work/ Piping Main.
Wilder Tower Transformers Replacement
Scope: Replace 1-480volt and 1-208volt transformer in the basement of Wilder Tower. Project
Manager is Jerome Moss (ext. 3140).
Impact Area: Entire Wilder Tower shutdown. Parts of Brister Hall shutdown.
Project Timelines: 12/26-28/25
Start and Stop Dates: 12/26/25 – 12/28/25
Building Name: Wilder Tower/Brister Hall
Room Numbers: Entire Buildings
Wilson Center (Holiday Inn) HVAC Replacements
Scope: Replace 3 hvac gas package units. Obtain fire marshall approval and associated inspections.
Project Manager is Swazoo Claybon (ext. 2076).