network iconThe Campus Network Upgrade Project

Project Description and Scope

Network Services (or Information Technology Services) will be upgrading the network infrastructure at all UofM locations. 
The project consists of 3 major phases:

  • Phase 1 – Replacement of network switches
  • Phase 2 - Replacement of wireless access points
  • Phase 3 – Replace of network access controller.

Note: These dates, times, and building schedule can be adjusted as needed.


Network Upgrade Frequently Asked Questions and Answers

Will the network be off-line during a specific timeframe? Does that mean that the network is unavailable during that time or just intermittently?
Assume that no network will be available during the entire time frame for your building's date.

Will phones be affected?
RingCentral phones will be unavailable during the switch replacement. Users can download the RingCentral and use their cell phone if needed.

Will I need to reboot my machine after the network upgrade is completed?
Yes, a reboot is suggested.

Will this affect my wireless connection?
Yes, your wireless connection will not be available during the building's switch over.

Who do I call if I my network is not working?
Call the Service Desk at 901.678.8888. Please let them know the building and room number you are calling about.


Network Upgrade Tentative Project Timeline

Information Technology Services (ITS) will launch a network upgrade to all buildings on campus beginning February 3, 2025. Below you will find a schedule of buildings with dates and expected outage times.​

Campus Building Date Outage Start Outage Finish Status Status
Main Finch-Center 2/4/25 6:00 AM 10:00 AM    
Main Rec Center 2/4/25 6:00 AM 10:00 AM    
Main Newport Hall 2/4/25 5:30 PM 11:00 PM    
Main Southern Garage 2/4/25 9:00 AM 2:00 PM    
Main Student Wellness Center 2/4/25 6:00 AM 10:00 AM    
Main Alumni Center 2/5/25 5:30 PM 11:00 PM    
Main Billy Mac Jones 2/5/25 5:30 PM 11:00 PM    
Main Athletic Office 2/6/25 5:30 PM 11:00 PM    
South Campus Baseball Stadium 2/10/25 9:00 AM 4:00 PM    
South Campus Golf 2/10/25 9:00 AM 4:00 PM    
South Campus Softball Annex 2/10/25 9:00 AM 4:00 PM    
South Campus Softball Stadium 2/10/25 9:00 AM 4:00 PM    
South Campus Football Complex 2/12/25 9:00 AM 4:00 PM    
South Campus Greenhouse 2/12/25 9:00 AM 4:00 PM    
South Campus Landscape 2/13/25 9:00 AM 4:00 PM    
South Campus South Campus Building 52 (Mail Service) 2/13/25 9:00 AM 4:00 PM    
South Campus Defense Audit 2/13/25 9:00 AM 4:00 PM    
South Campus Basketball 2/17/25 9:00 AM 4:00 PM    
South Campus South Campus Building 2 2/17/25 9:00 AM 4:00 PM    
South Campus South Campus Building 29 2/17/25 9:00 AM 4:00 PM    
Main Boiler Room 2/19/25 5:30 PM  11:00 PM    
Main Physical Plant 2/19/25 5:30 PM  11:00 PM    
Main Crews Venture Lab 2/20/25 5:30 PM  11:00 PM    
Main Honors Hall 2/20/25 5:30 PM  11:00 PM    
Main Information Center 2/20/25 9:00 AM  4:00 PM    
Main Industrial Art 2/24/25 5:30 PM  11:00 PM    
Main Scates Hall 2/24/25 5:30 PM  11:00 PM    
Main Wilson Hotel 2/24/25 11:00 PM 5:00 AM    
Main Browning Hall 2/25/25 5:30 PM  11:00 PM    
Main McCord Hall 2/26/25 5:30 PM  11:00 PM    
Main Hayden Hall 2/26/25 5:30 PM  11:00 PM    
Main Robison Hall 2/26/25 5:30 PM  11:00 PM    
Main International Center 2/27/25 5:30 PM  11:00 PM    
Main Meeman Journalism Building 2/27/25 5:30 PM 11:00 PM    
Main Student Health Center 3/3/25 5:30 PM 11:00 PM    
Main Clement Hall 3/4/25 5:30 PM 11:00 PM    
Main Mitchell Hall 3/5/25 5:30 PM 11:00 PM    
Main Ball Hall 3/5/25 5:30 PM 11:00 PM    
Main Life Sciences Building 3/5/25 5:30 PM 11:00 PM    
Main Ellington Hall 3/6/25 5:30 PM 11:00 PM    
Main Johnson Hall 3/6/25 5:30 PM 11:00 PM    
Main Law School 3/10-11/25 5:30 PM 11:00 PM    
Main Campus School 3/12/25 9:00 AM 4:00 PM    
Main Campus School Annex 3/12/25 9:00 AM 4:00 PM    
Main Zach Culin Parking Garage 3/12/25 9:00 AM 4:00 PM    
Main Lipman School 3/13/25 9:00 AM 4:00 PM    
Main Orgel 3/13/25 9:00 AM 4:00 PM    
Main Patterson Hall 3/17/25 5:30 PM 11:00 PM    
Main Manning Hall 3/18/25 5:30 PM 11:00 PM    
Main Dunn Hall 3/19/25 5:30 PM 11:00 PM    
Main Jones Hall 3/24/25 5:30 PM 11:00 PM    
Main Elma Roane Fieldhouse 3/25/25 5:30 PM 11:00 PM    
Main Smith Chemistry Building 3/26/25 5:30 PM 11:00 PM    
Main Psychology 3/27/25 5:30 PM 11:00 PM    
Main Psychology Auditorium 3/27/25 5:30 PM 11:00 PM    
Main Maxine A. Smith University Center 3/31/25 5:30 PM 11:00 PM    
Main Communication & Fine Arts Building 4/1/25 5:30 PM 11:00 PM    
Main Arts & Communication Building 4/2/25 5:30 PM 11:00 PM    
Main Fedex Institute of Technology 4/7/25 5:30 PM 11:00 PM    
Main Fedex institute of Technology (Boiler Room) 4/7/25 5:30 PM 11:00 PM    
Main Earthquake Center 4/8/25 5:30 PM 11:00 PM    
Main Scheidt Family Performing Art Center 4/9/25 5:30 PM 11:00 PM    
Main Edwards Research & Innovation Center 4/10/25 5:30 PM 11:00 PM    
Main Theater Building 4/14/25 5:30 PM 11:00 PM    
Millington Campus Millington Campus 4/18/25 8:00 AM 4:00 PM    
Main Community Health Building 4/21/25 5:30 PM 11:00 PM    
Chucalissa Chucalissa 4/22/25 9:00 AM 4:00 PM    
Cordova Campus Kemmons Wilson School of Hospitality and Resort Management 4/22/25 9:00 AM 4:00 PM    
Main Engineering Complex 5/13/25 5:30 PM 11:00 PM    
Main Carpenter Complex 5/15/25 8:00 AM 5:00 PM    
Main Rose Theater 3/17/25 5:30 PM 11:00 PM    
Main Centennial Place 5/19/25 8:00 AM 5:00 PM    
Main Rawls Hall 5/20/25 8:00 AM 5:00 PM    
Main Smith Hall 5/20/25 8:00 AM 5:00 PM    
Main South Hall 5/20/25 8:00 AM 5:00 PM    
Main Living Learning Center 5/21/25 8:00 AM 5:00 PM    
Main Graduate Student Family Housing 5/22-23/25 8:00 AM 5:00 PM    
Main V. Lane Rawlins Service Court Facility (Bookstore) 5/23/25 5:30 PM 11:00 PM    
Millington Campus Willis Hall 6/19/25 8:00 AM 5:00 PM    
Main Music Building 6/15/25 5:30 PM 11:00 PM    
Main McWherter Library 6/7/25 11:00 PM 5:00 AM